Cedar Road / Cedar Fairmount Program

Multiple Improvement Projects Scheduled

Construction season is upon us, and work will be starting within the Cedar-Fairmount Business District for a multitude of improvements. 

Resurfacing & New Streetscape

The City of Cleveland Heights is preparing to commence resurfacing Cedar Road along with a Streetscape within the Cedar-Fairmount Business District. 

Natural Gas Pipeline

Running Concurrently with the City’s project will be a natural gas pipeline replacement project through Dominion East Ohio, which is estimated to begin sometime in March.

Bid Award

The almost $4 Million Cedar Road Resurfacing/Cedar-Fairmount Streetscape was recently awarded to Perk Company, Inc., and is scheduled to begin in early Spring of 2017. 

Project Components

Resurfacing, ADA Compliant Curb Ramps, & Streetscapes

The project consists of Road Resurfacing and new ADA Compliant Curb Ramps from South Taylor Road to Euclid Heights Boulevard, as well as a Streetscape consisting of new trees, sidewalks, and sidewalk amenities from Fairmount Boulevard down to Euclid Heights Boulevard. 

Pedestrian & Bicycle Path

A multi-use pedestrian and bicycle path is to be constructed along Cedar Glen Parkway from Euclid Heights Boulevard to Ambleside Drive in Cleveland.

Project Funding

This project is being funded through the Federal Highway Administration, the Ohio Public Works Commission, and the Ohio Department of Natural Resources.

Project Updates

  1. July 21, 2017 Update
  2. July 14, 2017 Update
  3. June 16, 2017 Update
  4. May 19, 2017 Update
  5. May 12, 2017 Update
  6. May 8, 2017 Update
  7. April 17, 2017 Update
  8. April 7, 2017 Update
  9. April 3, 2017 Update
  10. March 24, 2017 Update
  11. March 17, 2017 Update

Progress

  • Pavement has been milled and the leveling course of asphalt has been laid from Euclid Heights Boulevard to Norfolk on the south side of Cedar Road. 
  • Perk has begun making full depth pavement repairs, and adjusting catch basin and manhole castings within the project phase.
  • The surface course of asphalt is scheduled to be laid next week from Norfolk to Westminster.
  • We have not experienced any set-backs.

Cedar Road Accelerated Pipeline Replacement PIR-2083

Red Dirt is wrapping the project up, waiting for the final go ahead from Dominion East Ohio.